Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 5/4/2022 - P69

Finance Committee - Agenda - 5/4/2022 - P69

By dnadmin on Sun, 11/06/2022 - 21:42
Document Date
Fri, 04/29/2022 - 14:39
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/04/2022 - 00:00
Page Number
69
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__050420…

C. CONTRACTOR is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that
may affect cost, progress, and performance of the Work.

D. CONTRACTOR has carefully studied all (if any): (1) reports of explorations and tests of subsurface
conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or
subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the
Supplementary Conditions as provided in paragraph 4.02 of the General Conditions and (2) reports and drawings of a
Hazardous Environmental Condition, if any, at the Site which has been identified in the Supplementary Conditions as
provided in paragraph 4.06 of the General Conditions.

CONTRACTOR is entitled to rely upon the general accuracy of the “technical data” as provided in paragraph 4.2 of the
General Conditions. CONTRACTOR acknowledges that such reports and drawings are not Contract Documents and may
not be complete for CONTRACTOR's purposes. CONTRACTOR acknowledges that OWNER and ENGINEER do not assume
responsibility for the accuracy or completeness of information and data shown or indicated in the Contract Documents
with respect to Underground Facilities at or contiguous to the site.

E. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having done so) all
additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions
(surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or
performance of the Work or which relate to any aspect of the means, methods, techniques, sequences and procedures
of construction, if any, expressly required by the Contract Documents to be employed by CONTRACTOR, and safety
precautions and programs incident thereto.

F. CONTRACTOR does not consider that any further examinations, investigations, explorations, tests,
studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in
accordance with the other terms and conditions of the Contract Documents.

G. CONTRACTOR is aware of the general nature of work to be performed by OWNER and others at the Site
that relates to the Work as indicated in the Contract Documents.

H. CONTRACTOR has correlated the information known to CONTRACTOR, information and observations
obtained from visits to the Site, reports and drawings identified in the Contract Documents and all additional
examinations, investigations, explorations, tests, studies, and data with the Contract Documents.

I. CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities or discrepancies that
CONTRACTOR has discovered in the Contract Documents, and the written resolution thereof by ENGINEER is acceptable
to CONTRACTOR.

J. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for performance and furnishing of the Work.

ARTICLE 8 - CONTRACT DOCUMENTS

8.01 Contents

A. 1. The Contract Documents are defined in Article 1 of the General Conditions as amended
herein.
2. The Construction Specifications and Contract Documents, dated March 2022.

AG - 4 0f 6