STANDARD FORM OF AGREEMENT
BETWEEN OWNER AND CONTRACTOR
THIS AGREEMENT is dated as of the day of in the year 2022 by and between
the City of Nashua, New Hampshire (hereinafter called OWNER) and New England Infrastructure, Inc.
and its successors, transferees and assignees together hereinafter called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows:
ARTICLE 1 - WORK
1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents.
ARTICLE 2 - THE PROJECT
2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is
generally described as follows:
The scheduled work for the Canal Street Bridge Repairs consists of concrete repair work on the east abutment and
the bridge pier.
ARTICLE 3 - ENGINEER
3,01 Division of Public Works
Engineering Department
9 Riverside Street
Nashua, NH 03062
is hereinafter called ENGINEER and who is to act as OWNER's representative, assume all duties and responsibilities, and
have the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the
Work in accordance with the Contract Documents.
ARTICLE 4 - CONTRACT TIMES
4.01 ‘Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and Completion and Readiness for final
payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Dates for Substantial Completion and Final Payment
Project will begin once a written “Notice to Proceed” is issued.
Substantial Completion shall be by October 28, 2022.
Substantial completion is defined in Section 1.01 of the General Terms and Conditions.
Final completion shall be by December 16, 2022.
AG - 1 of 6