SECTION 02745
ROAD RESTORATION
PART 1 - GENERAL
1.01
1.02
1.03
1.04
WORK INCLUDED:
Furnish all labor, equipment and materials required to install crushed gravel base
course, bituminous concrete pavement courses including temporary and permanent
trench paving curbing, sidewalks, disposal of excess material at the City landfill and
restoration of pavement markings in roadway areas where sewer and drainage
repairs are required, manholes are to be installed, manhole frames and covers are
replaced, or as ordered by the Engineer and as specified herein.
RELATED WORK:
Section 02300, EARTHWORK
Section 02085, POLY VINYL CHLORIDE GRAVITY PIPE AND FITTINGS
Section 02631, PRECAST MANHOLES
PAVEMENT DESCRIPTION:
GENERAL
In roadway areas where sewer and drainage repairs are required or ordered by the
Engineer, all trenched areas shall be paved with temporary bituminous pavement as
detailed on the plans as soon as practicable after installation of individual pipeline
segments, but no trench shall be without temporary pavement during the weekend
(Saturday & Sunday). After a minimum period of 45 days, the trench patch
pavement area shall be saw cut and removed beyond the limits of the trench, and
crushed gravel and binder and finish courses of pavement shall be installed as
detailed on the Contract Drawings, or as ordered by the Engineer. Miscellaneous
curbing and sidewalk disturbed by sewer and drainage installation shall be repaired
as detailed on the Contract Drawings, or as ordered by the Engineer.
REFERENCES
The following standards form a part of these specifications and indicate the
minimum standards required:
2022 Sewer Replacement Project Road Restoration
Nashua, NH 02745-1