SECTION 02530
BUILDING CONNECTIONS AND DROP CONNECTIONS
PART 1 - GENERAL
1.01 WORK INCLUDED:
A. This Section covers furnishing of all materials and labor to construct building sewer
connections and drop connections as indicated on the Drawings, and as herein
specified.
B. Final location of building connections shall be determined in the field by the Engineer.
1.02 RELATED WORK:
A. Section 02300, EARTHWORK
B. Section 02631, PRECAST MANHOLES AND CATCH BASINS
C. Section 02085, POLY VINYL CHLORIDE GRAVITY PIPE AND FITTINGS
1.03 SUBMITTALS: IN ACCORDANCE WITH REQUIREMENTS OF
GENERAL SPECIFICATIONS, SUBMIT THE FOLLOWING:
A. Electronic file consisting of shop drawings and manufacturers literature of the
materials of this section shall be submitted to the Engineer for review.
B. Shop drawings of any special connections, including the proposed adapters for service
connections, shall be submitted to the Engineer.
PART 2 — PRODUCTS
2.01 MATERIALS:
A. Pipe and fittings for drop connections and for gravity building connections shall be as
specified under Section 02085 POLYVINYL CHLORIDE GRAVITY PIPE AND
FITTINGS. Adaptors shall be as recommended by the pipe manufacturer.
B. — Concrete for encasement shall be as specified in Section 03302 FIELD
CONCRETE.
2022 Sewer Replacement Project Building Connections and Drop Connections
Nashua, NH 02530-1