SECTION
01330
SUBMITTALS
1. SHOP AND WORKING DRAWINGS
A.
D.
As required by the General Conditions, Contractor shall submit a schedule of shop and
working drawing submittals.
In accordance with the accepted schedule, the Contractor shall submit promptly to the
Engineer, through its authorized resident representative at the job site, or by mail,
three (3) copies each of shop or working drawings required as noted in the
specifications, of equipment, structural details and materials fabricated especially for
this Contract.
Such drawings shall show the principal dimensions, weight, structural and operating
features, space required, clearances, type and/or brand of finish of shop coat, grease
fittings, etc., depending on the subject of the drawings. When it is customary to do so,
when the dimensions are of particular importance, or when so specified, the drawings
shall be certified by the manufacturer or fabricator as correct for this Contract.
All shop and working drawings shall be submitted to the Engineer by and/or through
the Contractor, who shall be responsible for obtaining shop and working drawings
from his subcontractors and returning reviewed drawings to them.
Only drawings which have been prepared, checked and corrected by the fabricator
should be submitted to the Contractor by his subcontractors and vendors. Prior to
submitting drawings to the Engineer, the Contractor shall check thoroughly all such
drawings to satisfy himself/herself that the subject matter thereof conforms to the
Contract Documents in all respects. Shop drawings shall be reviewed and marked with
the date, checker's name and indication of the Contractor's approval, and only then
shall be submitted to the Engineer. Shop drawings unsatisfactory to the Contractor
shall be returned directly to their source for correction, without submittal to the
Engineer. Shop drawings submitted to the Engineer without the Contractor's approval
stamp and signature will be rejected. Any deviation from the Contract Documents
indicated on the shop drawings must be identified on the drawings and in a separate
submittal to the Engineer, as required under subsection 6.17 .Shop Drawings and
Samples; D. Submittal Procedures, Paragraph 3 of the General Conditions.
The Contractor shall be responsible for the prompt submittal and re-submittal, as
necessary, of all shop and working drawings so that there will be no delay in the work
due to the absence of such drawings.