T. PROTECTION OF LANDSCAPING
Contractor shall take appropriate measures to protect trees, shrubs and other landscaping.
Branches, limbs and roots shall not be cut except with permission of the Engineer.
Where cutting is necessary, work shall be performed by qualified workers.
Uz REMOVAL OF DEBRIS AND SURPLUS MATERIAL
Neither debris nor surplus material shall be deposited on private property.
Debris and surplus material shall be removed from the project area as promptly as
practical.
If the Contractor should fail to promptly remove debris or surplus material from the
project area, or if Contractor deposits same on private property, progress payment(s) may
be withheld.
V. PROTECTION OF MANHOLES AND PIPELINES
Appropriate measures will be taken to protect manholes and other structures as well as
pipelines from debris and other materials entering the system through open covers or
grates.
Should material enter the system or be deposited during or because of the Contractor’s
activities, this material shall be removed at the Contractor’s expense.
The Contractor may be required to clean structures and pipelines downstream of the
location where material entered the system.
The Contractor may be required to provide television inspection services to verify that
material has been removed.
WwW. DISPOSAL OF EXCESS MATERIAL
Excess excavated materials shall be disposed of at the Nashua Landfill. The tipping fee
for clean excess material shall be waived. Contractor shall make arrangements with the
Owner prior to hauling material to the landfill.
Material removed from sewer pipelines and manholes can be delivered and disposed of at
the Nashua Landfill provided the material has been decanted. There will be no fee for
this disposal.
X. WORK PLAN
The Contractor shall submit a Work Plan to the Engineer for acceptance prior to the start
of work on any street. In order to be considered acceptable the Work Plan must at a
minimum address the following:
>» Schedule for the work.
> Proposed method for communication with affected residents and businesses.