P. SUPERINTENDENCE OF THE WORK
Reference is made to General Conditions Section 6.01, Supervision and Superintendence.
Contractor shall provide appropriate onsite superintendence of all aspects of the work
whether performed by the Contractor or by subcontractors.
Qualified Superintendent(s) shall be assigned for all crews. Contact information will be
provided for all Superintendents.
Q. MAINTENANCE DURING WEATHER EVENTS
The Contractor’s obligation to protect the public traveling through the project site shall
include maintaining safe passage during rain and other weather events.
The Contractor shall plan in advance of forecasted inclement weather events and shall
assign crews to perform maintenance of unpaved areas open to traffic during and after
inclement weather events. Contractor is responsible to coordinate with the Engineer and
other City officials as appropriate.
R. CONTRACTOR’S REPRESENTATIVE
The Contractor shall designate a representative who will be available to respond to
emergency calls by the Owner at any time day and night and on weekends and holidays
should such a situation arise.
Should the City determine action by the City is needed, or if costs are incurred because the
Contractor’s Representative is not available, the City will backcharge the Contractor for
associated expenses.
S. SCHEDULING AND COORDINATION
Reference is made to General Conditions Section 2.05, Before Starting Construction and
General Conditions Section 6.04, Progress Schedule.
Prior to the start of construction, the Contractor shall submit a comprehensive schedule to
the Engineer for review and acceptance.
The schedule will identify the number of crews and completion dates for all critical
elements of work.
Detailed updates of the schedule shall be submitted to the Engineer for review and
acceptance on at least a monthly interval.
The Engineer may withhold progress payments if acceptable monthly schedule updates
are not submitted.
The Contractor shall not increase the number of crews assigned to the work as identified
in the schedule without providing one week advanced notice to the Engineer.