H. USE OF “TOKEN” QUANTITES FOR CONTRACT ITEMS
As noted in the Quantity Summary included in the Contract drawings, quantities
estimated for several Payment Items in the Contract are “token” quantities.
The purpose of these items and the corresponding token quantities is to facilitate
incorporation of possible additional work to this contract as described in Section G.
CHANGES TO THE CONTRACT WORK in these SUPPLEMENTARY
CONDITIONS.
At the time of advertisement for bids, it 1s anticipated that forty (40) sewer and/or
drainage point repairs will be required to address issues that arise from review of the
pipeline CCTV video assessment currently underway. This anticipated work is included
in the “token” quantities and Pay Items as presented in the Contract Drawings (Sheet 2 of
17- Quantity Sheet).
The amount bid for each of these items will be carefully reviewed for consistency with
other bid prices, and if an indication is found that an overall bid proposal may be
unbalanced, the City may reject the particular bid proposal as unbalanced.
The determination of whether a bid proposal is unbalanced shall be made entirely at the
City’s discretion.
I. PARKING REQUIREMENTS
The Contractor is responsible for obtaining the City official “No On-Street Parking” signs
when needed. These signs are available at the City Engineering Office. At the
completion of work, the signs shall be removed and returned to the City in good
condition.
J. COOPERATION WITH REFUSE PICKUP
Reference is made to General Conditions Section 17.09, Cooperation with Refuse Pickup.
Kk. HAZARDOUS ENVIRONMENTAL CONDITION
Reference is made to General Conditions Section 4.06, Hazardous Environmental
Condition at Site.
It is not anticipated that hazardous materials will be encountered during excavation for
the contract work.
However, the Contractor should be aware that as yet undiscovered areas with asbestos
containing material or other hazardous contaminants may be encountered.
An allowance (ITEM 10) has been incorporated into the contract to be used if, and only
if, hazardous material is encountered.
Should suspected hazardous material be encountered, the Contractor shall stop work and
immediately notify the Engineer.
2022 Sewer Replacement Project
Nashua, NH
SC - 4 of 8