Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Board Of Aldermen - Agenda - 4/12/2022 - P166

Board Of Aldermen - Agenda - 4/12/2022 - P166

By dnadmin on Mon, 11/07/2022 - 07:45
Document Date
Fri, 04/08/2022 - 13:45
Meeting Description
Board Of Aldermen
Document Type
Agenda
Meeting Date
Tue, 04/12/2022 - 00:00
Page Number
166
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/boa_a__041220…

a. Daniel Webster Highway

Night work may also be required on the above listed streets, depending on activity,
equipment and time of year.

Requests for work beyond those hours normally allowed on weekdays shall be made by
the Contractor at least 72 hours in advance.

Requests for work on Saturdays, Sundays and holidays shall be made at least one week in
advance.

Contractor should not assume requests for hours beyond the hours and days normally
allowed will be approved. Requests will be considered on a case by case basis.

Note: The City reserves the right to stop work should traffic controls prove to be
inadequate. Should a problem arise as a result of the approved traffic control plan,
additional traffic control measures may be required at the contractor ’s expense.

Contractor should not assume requests for hours beyond the hours and days normally
allowed will be approved. Requests will be considered on a case by case basis.

D. INTERIM SCHEDULE MILESTONES
In order to facilitate the 2022 Nashua Street Paving Program substantial completion of
work on the following streets shall be completed as required below:

" Fairview Avenue..... to be completed between June 27 to July 30, 2022.
* The Contractor shall prioritize point repair locations that interfere with the
2022 Nashua Street Paving Program

In order to accomodate the Rivier University class schedules, all work on Clement Street
to Daniel Webster Highway shall be completed between July 1 and August 15, 2022.

E. USE OF GROUNDS
Any area outside the limits of the project area (right-of-way within project limits) which
the Contractor may require for storage of equipment and materials, or for other purposes
necessary in the performance of the Work, shall be secured by the Contractor at their own
expense. Materials, including excavation intended for backfill, shall not be stored or
stacked within any roadway clear zones, or in a manner that obstructs adequate sight lines
unless specifically permitted in writing by the Engineer. The Contractor is responsible
for providing security as required and erosion controls at no cost to the City.

F. TRAFFIC CONTROL PLAN
Reference is made to Section 01110 Control of Work and Materials, Subsection 5
Maintenance of Traffic in the Construction Specifications.

2022 Sewer Replacement Project
Nashua, NH
SC - 2 of 8