CHANGE ORDER
No. 2
PROJECT: Nashua PD HVAC
OWNER’S CONTRACT NO: N/A
EXECUTED CONTRACT DATE: N/A
DATE OF ISSUANCE: 05-06-2021 EFFECTIVE DATE: N/A __
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 163567
CONTRACTOR: Turnstone Corporation
ENGINEER: Yeaton Associates, Inc.
You are directed to make the following changes in the Contract Documents:
Description:
6) Grid and Tiles (Criminal Investigation Division (CID) area, Locker Rooms, Interview Rooms)
7) Completion of the Firing Range Lighting
8) Firing Range Lighting Credit
9) Grid and Tiles (Report Writing/Records Area)
10) Electrical upgrade in the Report Writing Room
Justification:
6) New ceiling grid and tiles in the CID area, supervisor’s locker room, men and women’s locker
rooms, and interview rooms to replace original ceiling that is old, damaged, discolored and in
some locations missing.
7) Update the lighting in the firing range in accordance with the updates to the HVAC system.
This change order will cover the remainder of the project (last 7 rows of lighting).
8) Refund from Gate City Electric for firing range lighting unit that was not needed.