The schedule for the 1° year is shown below. We propose:
> A transition period of 2 month duration, by extending the current contractor for a period
of 2 months following start of our contract. During this period the current contractor will
gradually phase out its operations, as we assume ours.
> Formal training for a period of 4 month following | month of famtharization.
> The Bulletin Board be developed by BRBTV during month 2 of the contract, and go on-
line at the end of month 2.
> The Policy and Procedures Manual be produced in draft form for review by CTAB 2
month following start of contract, and finalized 3 months following start of contract.
>» The_Hosted programs produced by BRBTV begin | month after start of contract,
following a period of familiarization and execution of renewed host agreements.
> The Field Produced programs produced by BRBTV begin 3 months after start of contract,
following familiarization and training.
> Loaning out equipment to Nashua resident producers and broadcasting their contributions
by BRBTY begin 2 months after start of contract, following drafting of the various uscr-
oriented documentation and familiarization and training on the editing equipment.
> The Public Hearing be conducted at the end of month 11 of the contract.
> The Annual Survey be conducted in months 11 and 12 after start of contract.
We do not show a work plan and schedule for years 2 and 3 as this will be defined and proposed