§ 6.6.3 Fees and assessments for the building permit and for other permits, licenses and inspections for which the
Construction Manager is required by the Contract Documents to pay
§ 6.6.4 Fees of laboratories for tests required by the Contract Documents, except those related to defective or
nonconforming Work for which reimbursement is excluded by Section 13.5.3 of ALA Document A201 2007 or by
other provisions of the Contract Documents, and which do not fall within the scope of Section 6.7.3.
§ 6.6.5 Royalties and license fees paid for the use of a particular design, process or product required by the Contract
Documents; the cost of defending suits or claims for infringement of patent rights arising from such requirement of
the Contract Documents, and payments made in accordance with legal yudgments against the Construction Manager
resulting fom such suits or claims and payments of settlements made with the Owner’s consent. However, such
costs of legal defenses, judgments and settlements shall not be included in the calculation of the Construction
Manager’s Fee or subject to the Guaranteed Maximum Price. If such royalties, fees and costs are excluded by the
last sentence of Section 3.17 of AIA Document A201 2007 or other provisions of the Contract Documents, then
they shall not be included in the Cost of the Work.
§ 6.6.6 Costs for electronic equipment and software, directly related to the Work with the Owner’s prior approval
§ 6.6.7 Deposits tost for causes other than the Construction Manager's negligence or failure to fulfill a specific
responsibility in the Contract Documents
§
§ 6.6.9 Subject to the Owner's pnor approval, expenses incurred in accordance with the Construction Manager's
standard written personnel policy for relocation and temporary living allowances of the Construction Manager’s
personnel required for the Work.
§ 6.7 Other Costs and Emergencies
§ 6.7.1 Other costs incurred in the performance of the Work if, and to the extent, approved in advance in writing by
the Owner.
§ 6.7.2 Costs incurred in taking action to prevent threatened damage, injury or loss in case of an emergency affecting
the safety of persons and property, as provided in Section 10.4 of AIA Document A201-2007.
§ 6.7.3 Costs of repatring or correcting damaged or nonconforming Work executed by the Construction Manager,
Subcontractors or suppliers, provided that such damaged or nonconforming Work was not caused by neghgence or
failure to fulfill a specific responsibility of the Construction Manager and only to the extent that the cost of repair or
correction is not recovered by the Construction Manager from insurance, sureties, Subcontractors, suppliers, or
others
§ 6.7.4 The costs descnbed in Sections 6.1 through 6.7 shall be inctuded in the Cost of the Work, notwithstanding
any provision of AIA Document A20] 2007 or other Conditions of the Contract which may require the
Construction Manager to pay such costs, unless such costs are excluded by the provisions of Section 6.8
§ 6.8 Costs Not To Be Relmbursed
§ 6.8.1 The Cost of the Work shall not inctude the items listed below:
.1 Salaries and other compensation of the Construction Manager's personnel stationed at the Construction
Manager's principal office or offices other than the site office, except as specifically provided in
Section 6.2, or as may be provided in Article 11;
Expenses of the Construction Manager's principal office and offices other than the site office,
Overhead and general expenses, except as may be expressly included in Sections 6.1 to 6 7;
The Construction Manager's capitat expenses, including interest on the Constniction Manager's capital
employed for the Work,
6 Except as provided in Section 6.7.3 of this Agreement, costs due to the negligence or faiture of the
Construction Manager, Subcontractors and suppliers or anyone directly or indirectly employed by any
of them or for whose acts any of them may be liable to fulfill a specific responsibility of the Contract;
6 Any cost not specifically and expressly described in Sections 6.1 to 6.7,
mw io
AlA Document A133” - 2009 (formerly A1Z21™CiMtc = 2003). Copyright © 1991, 2003 and 2009 by The American Inslilute af Architects All rights reserved
Init The “American Inslitule ol Architecis.” “AIA.” Ihe AIA Logo. and “AIA Contract Documents” are registered rademasks and may not be used wilhoul permission 12
This document was produced by AIA software at 19:15.33 ET on 05/04/2021 under Order No.4 797552925 which expwes on 09/23/2021, is not for resale, is
i bcensed for one-time use only. and may only be used in accordance with ihe AIA Contract Documents*® Terms of Service. To report copyright violations, e-mail
copyright@aia org
User Notes (389ADA4E)