§ 2.3.2.5 The Construction Manager shall schedule and conduct meetings to discuss such matters as procedures,
progress, coordination, scheduling, and status of the Work. The Construction Manager shall prepare and promptly
distribute minutes to the Owner and Architect
§ 2.3.2.6 Upon the execution of the Guaranteed Maximum Price Amendment, the Construction Manager skal!
prepare and submit to the Owner and Architect a construction schedule for the Work and submittal schedule in
accordance with Section 3.10 of A201-2007
§ 2.3.2.7 The Construction Manager shall record the progress of the Project On a monthly basis, or otherwise as
agreed to by the Owner, the Construction Manager shall submit written progress reports to the Owner and Architect,
showing percentages of completion and other information required by the Owner. The Construction Manager shall
also keep, and make available to the Owner and Architect, a daily log containing a record for each day of weather,
portions of the Work in progress, number of workers on site, identification of equipment on site, problems that
might affect progress of the work, accidents, injuries, and other information required by the Owner.
§ 2.3.2.8 The Construction Manager shall develop a system of cost control for the Work, including regular
monitoring of actual costs for activities in progress and estimates for uncompleted tasks and proposed changes. The
Construction Manager shall identify variances between actual and estimated costs and report the variances to the
Owner and Architect and shall provide this information in its monthly reports to the Owner and Architect, in
accordance with Section 2.3.2.7 above.
§ 2.4 Professional Services
Section 3.12.10 of A201 2007 shall apply to both the Preconstruction and Construction Phases.
§ 2.5 Hazardous Materials
Section 10.3 of A201 2007 shall apply to both the Preconstruction and Construction Phases
ARTICLE 3 OWNER'S RESPONSIBILITIES
§ 3.1 Information and Services Required of the Owner
§ 3.1.1 The Owner shall provide information with reasonable promptness, regarding requirements for and limitations
on the Project, including a written program which shall set forth the Owner’s objectives, constraints, and criteria,
inctuding schedule, space requirements and relationships, flexibitity and expandability, special equipment, systems,
sustainability and site requirements.
§ 3.1.2 Prior to the execution of the Guaranteed Maximum Price Amendment, the Construction Manager may request
in writing that the Owner provide reasonable evidence that the Owner has made financial arrangements to fulfill the
Owner's obligations under the Contract. Thereafter, the Construction Manager may only request such evidence if ([)
the Owner fails to make payments to the Construction Manager as the Contract Documents require, (2) a change in
the Work materially changes the Contract Sum, or (3) the Construction Manager identifies in writing a reasonable
concern regarding the Owner's ability to make payment when due The Owner shall furnish such evidence as a
condition precedent to commencement or continuation of the Work or the portion of the Work affected by a maternal
change Aftec the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements
without prior notice to the Construction Manager and Architect
§ 3.1.3 The Owner shall establish and periodically update the Owner’s budget for the Project, including (1) the
budget for the Cost of the Work as defined in Section 6.1.1, (2) the Owner's other costs, and (3) reasonable
contingencies related to afl of these costs. [f the Owner significantly increases or decreases the Owner’s budget for
the Cost of the Work, the Owner shall notify the Construction Manager and Architect. The Owner and the Architect,
in consultation with the Construction Manager, shall thereafter agree to a commesponding change in the Project's
scope and quality.
§ 3.1.4 Structural and Environmental Tests, Surveys and Reports. During the Preconstruction Phase, the Owner shall
furnish the following information or services with reasonable promptness. The Owner shall also furnish any other
information or services under the Owner's control and relevant to the Construction Manager’s performance of the
Work with reasonable promptness after receiving the Construction Manager’s written request for such information
or services. The Construction Manager shall be entitled to rely on the accuracy of information and services furnished
by the Owner bul shall exercise proper precautions relating to the safe performance of the Work
. AIA Document A133” = 2009 (formerly A121™CMc — 2003) Copyright © 1991, 2003 and 2009 by The Amencan Inslitule of Architects. All rights reserved
Init. The “Amencar: Instiute of Archilects.” ‘AIA,” the AIA Logo, and “AIA Contract Documents’ are registered trademarks and may not be used witnoul permission
This document was produced by AIA sofh at 41:15:33 ET on 05/0412021 under Order No.4797552925 which expires on 09/2¥2021. is not for casate, is
kcensed for one-lime use only, and may only be used in accordance wilh Ihe AIA Contract Oocuments® Terms of Service. To report copyright violalions, e-mail
copyright @aia.org.
User Notes: (JB9ADA4E)