2. Paragraph IV (B) (1) shall be MODIFIED as follows;
B. Limits of All Payments
1. The ENGINEER hereby assures the OWNER and agrees that the following fee for his services
(exclusive of surveys, borings, and certain special services which follow) in connection with the
preparation of final plans, specifications, and contract documents and other work as generally described
under I(A) is adequate to complete the assignment and shall not exceed:
To be determined Dollars ($TBD) for the Dry Well Valve and Pipe Replacement
Engineering Design; and
Seventy-Eight Thousand Three Hundred and 00/100 Dollars ($78,300.00) for the
Wash Press Chute Modifications and the Screening Garage Odor Engineering Design.
IN WITNESS WHEREOF, the parties hereto have made and executed this AMENDMENT to said AGREEMENT as of
the day and year first above written.
ENGINEER:
WRIGHT-PIERCE
By:
(Authorized Representative *)
Date:
OWNER:
CITY OF NASHUA
By:
(Authorized Representative *)
Date:
APPROVED:
DEPARTMENT OF ENVIRONMENTAL SERVICES
Water Division
By:
(Authorized Representative **)
Date:
Signatures should be supported by appropriate document.
It is agreed that as an act in furtherance of its statutory authority to approve engineering agreements for treatment works, the
DIVISION's approval does not impose any contractual obligation or liability on the State of New Hampshire, the Department of
Environmental Services or the Division.
Page 3 of 3