AMENDMENT NO.1
TO
AGREEMENT BETWEEN
CITY OF NASHUA, NEW HAMPSHIRE
AND
WRIGHT-PIERCE
FOR
ENGINEERING DESIGN SERVICES
This AMENDMENT No.1 made the day of. , 2022, by and between The City of Nashua, New
Hampshire, (hereinafter called OWNER), and Wright-Pierce (hereinafter called ENGINEER).
WHEREAS, an AGREEMENT was entered into on January 10, 2022 between the OWNER and
ENGINEER, which AGREEMENT is entitled “Engineering Design Phase.”
hereinafter referred to as AGREEMENT.
WHEREAS, the OWNER desires the ENGINEER to perform additional design engineering for two (2)
additional projects that are located in the same general vicinity as the Dry Well Valve and Replacement design
project. These two (2) additional design projects, in addition to the Dry Well Valve and Replacement design
project, were recommended in the” Nashua WWTF 20-Year Facility Engineering Report, date July 28,
2021”. Amendment 1 Scope of Work, attached as EXHIBIT A - AMENDMENT 1 and Fee Schedule,
attached as EXHIBIT B - AMENDMENT 1.
Payment will be made in accordance with the original agreement based on hours and rates by labor category
with mark-up and incidental expenses in accordance with the attached fee, as modified for this amendment.
Original Amend-1 Amended
Tasks Contract Amount Contract
Amount Amount
Preliminary Design Dry Well and Pipe
Replacement
Initial Planning and Investigations $18,724 $0.00 $18,724
Preliminary Design Development $54,375 $0.00 $54,375
Prepare Draft Preliminary Drawings $27,351 $0.00 $27,351
Finalize Preliminary Design Report $5,350 $0.00 $5,350
Wash Press Chute Modifications
Preliminary Design $0.00 $12,553 $12,553
Final Design $0.00 $15,894 $15,894
Bidding Allowance $0.00 $553 $553
Screening Garage Odor Control
Preliminary Design $0.00 $13,528 $13,528
Final Design $0.00 $35,141 $35,141
Bidding Allowance $0.00 $631 $631
TOTALS | $105,800 $78,300 $184,100