Site Work Phasing Narrative
Phase 1 South Side Transit Station
Widening of parking lot entrance
Develop new traffic route for busses on north side of transit center
Saw cutting pavement along elm street, transit station platform,
remove and reset curbs along transit center platform and south parking lot.
construct full depth pavement to top of binder course
construct drainage improvements
removal and storage of brick where needed
Landscaping
Ramp hand rail
installation of benches and bike racks
Removal of pavement markings
Adjustment of elm street travel lanes
Construction of sidewalks along elm, around parking lot, and around transit station.
Phase 2 North West Side Parking Garage
construct north curb along elm and parking garage
Drainage work as night work.
remove and dispose of north side garden street sidewalk
saw Cutting the rest of elm street
remove and reset pay parking meter
Remove existing pavement and sub-base
installation of benches
Landscaping (planting of flowers, shrubs, pine bark mulch)
elm street travel lanes adjusted in phase 1 to remain
Phase 3 North East Side Parking Garage
Construct drainage curb and sidewalk
Saw cutting near parking garage and along street
remove and reset curb
remove and dispose of existing concrete side walk
Landscaping