3) New ceiling tiles and grid to replace original ceiling that is old, damaged, discolored and in
some locations missing.
4) Update the lighting in the firing range in accordance with the updates to the HVAC system.
This change order will cover 1 row of lights only (The remaining rows of lights will be
installed at a later date and will require an additional change order at that time).
5) Roll call room HVAC expansion. The roll call room HVAC will be adjusted to accommodate
the size of the roll call room.
Summary
No. 1
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
3,601,767.00 Substantia! completion:
Ready for final payment:
Net changes from previous Change Orders Net change from previous Change Orders
$0.00
Contract Price prior to this Change Order Contract Times prior to this Change Order
$3,601,767.00 Substantial completion:
Ready for final payment:
Net Increase édecreasejof this Change Order Net Increase (decrease) of this Change Order
25,840.39
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
3,627,607.39 Substantial completion:
Ready for final payment:
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
, Director Mayor Jim Donchess
(Authorized Signature) (Authorized Signature) Owner
{Authorized Signature)
Date: / Ly [ti Date:
Date: