CHANGE ORDER
No. 1
PROJECT: Nashua PD HVAC
OWNER’S CONTRACT NO: N/A
EXECUTED CONTRACT DATE: N/A
DATE OF ISSUANCE; 05-06-2021 EFFECTIVE DATE: N/A____
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 163567
CONTRACTOR: Turnstone Corporation
ENGINEER: Yeaton Associates, Inc.
You are directed to make the following changes in the Contract Documents:
Description:
1) Cooling in Data Closets 113A & 218A
2) Shaft Fire Dampers
3) Tiles and Grid
4) Firing Range Lighting (1 Row Only)
5) Roll Call Room HVAC Extension
Justification:
1) Due to the presence of information technology hardware and components that have been
moved into this closet over the years, and the excessive heat that the equipment generates, the
need for the room to have its own temperature control and regulation was identified.
2) During the course of the installation of the new HVAC system components, it was identified
that these fire dampers needed to be installed in order to bring the system into compliance with
code.