“BRB”
B = Desirable (second priority): Programs/Projects which will benefit the community whose validity of planning and timing have
been established.
PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.I.C
REQUESTED RECOMMENDS
Division of Annual Drainage
B-1 Public Works Improvements
(Engineering) $ 75,000 $ 75,000
At numerous locations drainage issues exist where runoff during large rain events impacts the roadway and private
properties. Some of the problematic locations include Wilmington Rd at New Searles Rd, Knowlton Rd, Westchester
Dr. and Pemberton Rd at Belfast St. A variety of solutions such as infiltration and drainage system extension will be
used to mitigate the issues.
Division of Vehicular and Pedestrian
B-1 Public Works Bridge Rehabilitation Program
(Engineering) $ 100,000 $ 100,000
The closure of a bridge is very disruptive to the public, including pedestrian bridges that provide key connectivity in
the downtown and parks. Inspection reports have identified several bridges with notable deficiencies to be
addressed in a reasonable timeframe. This request is for funds for professional services to develop a
comprehensive asset management plan for bridge maintenance, repair and upgrade.
Division of Stadium Drive Facility
B-1 Public Works Roof Replacement
(Street Department) $ 1,320,000 $ 1,320,000
The existing roof membrane was installed in 1978-79 and is approximately 75,000 square feet. There are multiple
areas that are leaking and need repair.
Division of West Hollis Street
B-2 Public Works Corridor Improvements
(Engineering) $ 95,000 $ 95,000
Sidewalks, crosswalks, bicycle accommodation, lighting and traffic calming measures are needed along the West
Hollis Street corridor to improve safety/efficiency of pedestrian and vehicular travel west of Riverside Street.
Complaints are frequently received about difficulty entering/departing the corridor from abutting residential streets. A
traffic signal or other measure is needed to mitigate high traffic volumes including trucks to/from the landfill.
11