PRIORITY DEPARTMENTS PROJECTS DEPARTMENT C.1.C
REQUESTED RECOMMENDS
Division of Taylor Falls and
A-2 Public Works Veterans Bridges
(Engineering) Deck Rehabilitation $ 550,000 $ 550,000
The failure of a bridge can be more disruptive to the traveling public than any roadway element and can also create a
safety concern. A 2018 inspection and report by an engineering consultant recommends rehabilitating the decks of
these two bridges within the next few years. If left unaddressed, the decks will need to be completely replaced in
about 10 years at a significantly higher cost. State aid is unlikely to be awarded within the 10-year timeframe;
however, the Town of Hudson will pay for 50% of design and construction costs since they are co-owners of the
bridges.
TOTAL FY 2022 LONG-TERM "A" PROGRAMS: $ 8,600,000 $ 8,600,000
10