City of Nashua, Public Works Division
Board of Public Works Meeting Date: February 25, 2021
Daniel Hudson, P.E., City Engineer
Engineering Department
2021 CIPP Lining Program - Construction
‘To approve the award of the construction contract for the 2021 CIPP Lining Program to
Green Mountain Pipeline Services, LLC of Bethel, VT in the amount of $1,990,745.39
pending bond approval. Funding will be through: Department: 169 Wastewater; Fund:
Bond; Activity: Sewer Rehab.
The annual sewer program addresses failing, aged sewers and associated structures and
piping. This 2021 CIPP (Cured-in-Place-Pipe) Lining program is expected to video
inspect approximately 80,000 feet of sewer pipe, line approximately 32,000 feet of sewer
pipe and rehabilitate approximately 120 sewer structures. Pipe lining is significantly less
expensive and less disruptive than full pipe replacement, and is instrumental in
rehabilitating the City’s sewer infrastructure.
Five bids were received on February 8th as follows:
Green Mountain Pipeline Services, LLC of Bethel, VT $1,990,745.39
Kenyon Pipeline Inspection of Queensbury, NY $2,071,630.00
National Water Main Cleaning Co. of Canton, MA $1,997,496.40
Granite Inliner of Orleans, IN $2,146,287.70
Insituform Technologies of Chesterfield, MO $1,997,406.00
The low bid was reviewed and found to be acceptable. Green Mountain has performed
well on other sewer projects with other public works entities in New Hampshire based
on review of previous projects and references. Work is planned to start in April.