City of Nashua, Public Works Division
Board of Public Works Meeting Date: March 25, 2021
Daniel Hudson, P.E., City Engineer
Engineering Department
Sewer Replacement Program — SUR West Change Order No. 3
To approve Change Order No. 3 to the 2020 Sewer Replacement Project with SUR
Construction West, Inc. of Winchester, NH for an amount not to exceed $1,300,000.
Funding will be through Department: 169 Wastewater; Fund: Bonded; Activity: Sewer
Repair.
2020 Sewer Replacement Project, Change Order No. 3
SUR Construction West was contracted for 2020 Sewer Replacement work under
IFB0779-021220, has been underway since early April 2020, and we have found their
work to be excellent and reasonably priced. Through completed Close Circuit Television
(CCTV) pipe inspection work, we have identified additional sewer pipe that needs repair
or replacement. The purpose of this Change Order is to expand SUR Construction West’s
contract to include replacement of additional deteriorated sewer pipes.
The above change order will allow for repair or replacement of deteriorated pipe segments
and accompanying sewer structures and sewer services, if necessary. If portions of these
pipes are found to be in sattsfactory condition, or suitable for lining, they will be retained
and funds used for repair or replacement of other sewer pipes and structures found to be
in disrepair through the City’s ongoing CCTV work.