Third, we will coordinate with the various utility companies to keep the outside work on track and
hopefully bring this aspect of the project to fruition by April. Our goal is start major demolition in April,
which is when you will see the “newer” portion of 201 Main Street, 1.c. the 1960s/1970s era building
come down and be demolished. This task will take approximately one month.
Finally, West Pearl Street will at some point over the next 4 to 6 weeks go down to one (1) lane of traffic
and at times maybe shut completely for sporadic deliveries. The sidewalk along Main Street may be
turned off at certain points (and for long periods of time) due to unsafe conditions for a pedestrian(s) to be
in a close vicinity of the construction (this will be particularly true during the exterior demolition phase of
the project).
In conclusion, should you or your constituents care to discuss this topic in greater detail please do not
hesitate to reach out to me at your earliest convenience.
Thank You.