PRESERVATION COMPANY
DETAILED COST BREAKDOWN
EAST HOLLIS STREET AND BRIDGE STREET IMPROVEMENT PROJECT - FINAL DESIGN
NASHUA, NH
December 1, 2021 gk fol
P AH Il AHI TOTAL DIRECT
TASK _ TASK DESCRIPTION $50.00 | $45.00 | $40.00 HOURS LABOR
PHASE 2 PRELIMINARY DESIGN
IIC Environmental Documentation 115 60 220 395 $ 17,250.00
Prepare NHDHR Historic District Area Form 65 100 30
Fieldwork 10 (¢] 10
Research (4) 40 30
New Individual Survey Forms £4} (2) 20 20 20
Update tadiidual Survey Forms {45} (¢] (¢] (¢]
Effects Tables 20 (4) 30
PRESERVATION COMPANY DIRECT LABOR TOTAL =| $ 17,250.00
Overhead @ 98.00% =| $ 16,905.00
Sub-Total =| $ 34,155.00
Fixed Fee @10% =| $ 3,415.50
PRESERVATION COMPANY TOTAL ESTIMATED LABOR COST =| $ 37,570.50
DIRECT EXPENSES
Transportation] $ 280.00
Mailings] $ 60.00
PRESERVATION COMPANY TOTAL ESTIMATED DIRECT EXPENSES =] $ 340.00
TOTAL PRESERVATION COMPANY ESTIMATED COST =] $ 37,910.50
Page 7 of 8