Total Commercial/Industrial/Exempt Improved Parcel Count
Total Measures 0
Total Interior Inspections = 0
Entry Rate 0%
Total Percent Complete Measured 0%
Refusals to Date 0
Building permits measured to date 89
Task 300/400
e Residential valuation is scheduled to commence in 2022.
e Preliminary analysis in 2022
1,964
¢ Income and Expense forms are being sent out by the Assessor's office.
Task 500/600
* Field review is scheduled te be completed in 2022.
Task 900
e The following timetable is for the hearing phase of the job through the
project’s completion.
Impact notice mailing no later than July 2022.
Hearings scheduled for July/August 2022.
Second Lmpact Notices mailed by August 2022.
Project Completed by September |, 2022.
= 9 8 © @
Ifyou should have any questions, please do nat hesitate to call.
Sincerely,
June Perry
Project Manager
508-351-3634
Appointments taken for hearings scheduled for July/August 2022.