SOVER
Project Status Report
From June Perry
Clty of Nashua NH
Date: May 2, 2020
CODE TASK
190 Bonding, Office Set-up, Project Set-up, Public Relations
200 Data Collection, Data Mailers, Building Permits, Sales
Inspections, Quality Control and Data Entry
300 Residential Valuation
400 Commiercial/Industrial Valuation
500 Residential Field Review, Data Entry
600 Commercial/Industrial Field review, Income Production,
Reconcile Cost and Income
700 Digital Imaging, Documentation
900/ Project Finalization, Change Notices, Special Land Pricing,
1000 Client Meetings, Support of Values, Goodwill
Task 100/200
e Bonding is complete. GIS maps have been provided. Building permits are being
completed by the City through April 1, 2020. Vision is responsible for building
permits though April 1, 2022,
e Public Relations will be on going throughout the project, with on-going sample press
releases provided, and meetings available upon request.
Updates will be provided throughout the project.
The initial startup meeting with the Board and DRA was March 2, 2020 at City Hall.