Project Status Report
From June Perry
City of Nashua NH
Date: April 25, 2020
CODE TASK
100 Bonding, Office Set-up, Project Set-up, Public Relations
200 Data Collection, Data Mailers, Building Permits, Sales
Inspections, Quality Control and Data Entry
300 Residential Valuation
400 Commercial/Industrial Valuation
500 Residential Field Review, Data Entry
609 Commercial‘Industrial Field review, Income Production,
Reconcile Cast and lacome
700 Digital Imaging, Documentation
900/ | Project Finalization, Change Notices, Special Land Pricing,
1000 Client Meetings, Support of Values, Goodwill
Fask 100/200
Bonding is complete. GIS maps have been provided. Building permits are being
completed by the City through April [, 2020. Vision is responsible for building
permits though April 1, 2022.
¢ Public Relations will be on going throughout the project, with on-going sample press
releases provided, and meetings available upon request.
e Updates will be provided throughout the project.
* ‘The initial startup meeting with the Board and DRA was March 2, 2020 at City Hall.