Total Commercial/Industrial/Exempt Improved Parcel Count
Total Measures 0
Total Interior Inspections 4
Entry Rate 0%
Total Percent Complete Measured 0%
Refusals to Date 0
Task 300/406
* Residential valuation is scheduled to commence in 2022,
e Preliminary analysis in 2022
1,964
* Income and Expense forms are being sent out by the Assessor's office.
Task 500/600
« Field review is scheduled to be completed in 2022.
Task $66
© The following timetable ts for the hearing phase of the job through the
project’s completion,
impact notice mailing no later than July 2022.
Hearings scheduled for July/August 2022.
Second Impact Notices mailed by August 2022.
Project Completed by September 1, 2022.
* 8 8® 8 @
ifyou should have any questions, please do not hesitate to call.
Stncerely,
June Perry
Project Manager
508-351-3634
Appointments taken for hearings scheduled for July/August 2022.