Total Commercial/Industrial/Exempt Improved Parcel Count
Total Measures 0
Total Interior Inspections 0
Entry Rate 0%
Total Percent Complete Measured 06%
Refusals to Date 0
Task 300/400
e Residential valuation is scheduled to commence in 2022.
e Preliminary analysis in 2022
£964
« Income and Expense forms are being sent out by the Assessor's office.
Task 500/600
* Field review is scheduled to be completed in 2022,
Task 900
» The following timetable ts for the hearing phase of the job through the
project’s completion.
Impact notice mailing no later than July 2022.
Hearings scheduled for July/August 2022.
Second Impact Notices mailed by August 2022.
Project Completed by September |, 2022.
5 ¢ 3 & &
Ifyou should have any questions, please do not hesitate te cail.
Stacerely,
June Perry
Project Manager
508-351-3634
Appointments taken for hearings scheduled for July/August 2022.