Project commenced March 3%, 2020,
Data Collection guidelines have been completed. Lister’s information has been
completed and the police department has been informed of all aspects of the data
collection phase of the revaluation.
Data entry will be ongoing throughout the project, commencing after June 2020.
Usernames and passwords have been assigned, and will have people associated with
them as me move closer to starting the data entry.
Daily communication with the Assessor's office is on-going concerning the progress
cf the data collection as well as any issues to be addressed,
Rick Kulp is the onsite Projects Staff Appraiser.
Ward | Property record cards have been printed.
Ward 2 is scheduled to be printed next.
[mages are being taken and will coincide with production numbers.
The database Is live in Nashua NH
Data collection has started tn Ward |
Ward 1 count 3,869
The following is the measure and listing numbers accountable as of March 7, 2020
Total Residential Improved Parcel Count 25,605
Measures 210
Total Interior Inspections 83
Refusals to Date - Partial/Full WT
Total Measures with refusal 2197
Entry Rate 39%
Entry rate with refusals 45%
Total Percent Complete Measured .08%
Appointments to date