July 34, 2020
Following are descriptions of the proposed scope of services specific to each project component
shown above.
2.12.1 - Factory St. Extension Ped Access to Pine Street
This task has evolved to include a new ped crossing on Pine Street with appropriate
pavement markings, signage and possibly flashing beacons. VHB will complete this
preliminary design. Minor streetscape modifications at the entrance to Factory Street
Extension that would give the appearance that the street is intended for pedestrians have
been considered, but the assumption at this time is that the area will not be improved until
after the redevelopment of the Picker Building since their plans are still pending.
Lead Project Team Consultant: VHB
Support from: Halvorson
2.12.2 - Redesign of Factory St Extension:
This area will include modifications to the existing Factory St Extension to better
accommodate pedestrians and bicyclists, but to continue to provide access for emergency
vehicles and maintenance operations. The improvemenis are expected to include lighting,
new pedestrian railings, planters and possibly dumpsier screening. The design does not
include an over-water section of path to preserve parking in the vicinity of Perk de la
Renaissance, but rather assumes that some parking will be displaced to make room fora
path connection, as discussed with the property owners.
Halvorson will do all the preliminary streetscape design reflecting on the conceptual
design images, and VHB will provide input on the railings and the roadway reconstruction
typical section. Detailed plans and grading are not included in this phase.
[t is assumed the design will not commence uniil the City obtains an answer from the
Millyard Associates on the disposition of the existing sewer line under the roadway since
that could affect the planned improvements. This scope of services does not currently
include sewer evaluation or design.
Lead Consultant: Halvorson
Support from: VHB
2.12.3 - Parc de la Renaissance Design and Water and Factory St Parking
The preliminary design in this area will include further development of the park design.
The design will include filling lands adjacent to Water Street to create an amphitheater,
new pathways, revised parking, waterfront plazas and landscape enhancements that
include planting, hardscape, street furnishings and lighting. This area may also be explored