vivo Design Services & Project Management of Downtown Riverfront Implementation
duly 31, 2020
AMENDMENT FOR PROFESSIONAL SERVICES
BETWEEN
VANASSE HANGEN BRUSTLIN, INC.
AND
THE CITY OF NASHUA, NEW HAMPSHIRE
DOWNTOWN RIVERFRONT PROJECT
July 31, 2020
The following amends the existing agreement between the City of Nashua and Vanasse Hangen
Brustlin, Inc. (VHB) for the Nashua Downtown Riverfront Project dated 12/12/2019. This
amendment is subject to the terms and conditions of the original contract.
PROJECT LIMITS
The project limits have expanded from those described in the original contract. By way of this
amendment the project boundaries along the Nashua River are expanded to include the
northern riverfront east of the Margaritas restaurant to and including the pedestrian walkway on
the PanAm bridge, and along the south side of the river from Main Street east past the PanAm
bridge to Temple Street. The project area continues to include the north and south sides of the
river from Pine Street and the Broad Street Parkway eastward to Main Street.
SCOPE OF SERVICES
The scope of services covered by this amendment inciudes the work under the following phase:
2 Phase 2— Preliminary Design (Schematic Design)
The scope of services for Phase 3 Final Design (Design Development) will be added by contract
amendment at a later date when the scope is well defined.
PHASE 2 — PRELIMINARY DESIGN
The preliminary design phase will build on the work and design decisions made in the phase 1
conceptual design phase. Whereas the conceptual design was largely a 2-dimensional (2D)
design with assorted sketches, details, visualizations and plans, the preliminary design will evolve
into a 3-dimensional (3D) design. This will be done using the survey base plans provided by
rlayner-Swanson Inc. (HIS) working directly for the City. Preliminary design will only commence