Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Board Of Aldermen - Agenda - 8/11/2020 - P88

Board Of Aldermen - Agenda - 8/11/2020 - P88

By dnadmin on Sun, 11/06/2022 - 23:05
Document Date
Fri, 08/07/2020 - 15:09
Meeting Description
Board Of Aldermen
Document Type
Agenda
Meeting Date
Tue, 08/11/2020 - 00:00
Page Number
88
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/boa_a__081120…

hb Design Services & Project Management of Downtown Riverfront Implementation

October 31, 7019

as the conceptual design of the entire project progresses. It will be important to integrate their
current lighting designs into any new work planned under this profect. The current
understanding ts that most if not all of the proposed Riverfront lighting will be built as part of
this project.

Product: Plans, details and images to illustrate the proposed conceptual imprayemenis.

Lead Consultant: Lumen Design Studio
support from: Fitzemeyer & Tocci, VAB
Estimated Duration: 8 weeks

i7 Wayfinding

The City is currently advancing a downtown waytinding plan designed by others. For the
Riverfront project VHB will at most identify the conceptual recommended locations for
wayfinding signage during the conceptual Stage, but actual wayfinding sign development will be
advenced in a later phase. For Phase 1 the waytinding efforts will only include identifying
conceptual sign placement locations and potential general conteni,

Lead Consultant: VAB
Support from: Halvorson
Estirnated Duration: 1 week, toward the end of Phase 1

LS Permittina Considerations

Permit applications will be prepared after Phase 2, but during Phase 1 the design team will be
cognizant of the potential permitting implications of every aspect of the design when important
design Gecisions are being made. Section 7 of the Riverfront Plan included a relatively
exhaustive evaluation of the permitting landscape for this project. As the design prograsses,
however, VHB environmental specialists will advise tha design team relative to any permitting
implications. In addition, The HL Turner Group will provide crucial input on any in-stream or
shoreline work that could potentially affect flood levels, # su b-projects are identified for
accelerated schedules it will be important to demonstrate that they have independent utility and
can be permitted on their own rather than waiting for the entire project to be permitted.

Lead Consultant: VHB
Support jrom: HL Turner, Halvorson
Estimated Duration: throughout Phase 1

1.9 Conceptual Cost Estimating

VHB will manage and assemble cost estimates for each of the project components fram the
design team members in their respective disciplines, The HL Turner Group will provide costs for

Jaa

Bo